# Babcock & Wilcox account plan

> Babcock & Wilcox is an Akron, Ohio energy technology firm selling boilers, parts and power plants; FY2025 revenue $587.7 million, backlog $2.5 billion.

## At a glance

Babcock & Wilcox Enterprises (NYSE: BW), headquartered in Akron, Ohio, supplies steam generation equipment, aftermarket parts, construction and field services, and emissions control and carbon capture technologies to utilities, industrial plants and, increasingly, data centers. It has nearly 160 years of history and an installed base it services for itself and other manufacturers. After divesting Vølund, Diamond Power and ASH in 2025, FY2025 revenue from continuing operations was $587.7 million, with operating income of $20.7 million and adjusted EBITDA of $43.7 million; it had about 1,650 employees at December 31, 2025. Kenneth Young is Chairman and CEO, and B. Riley holds about 22.1% of the voting power.

## Business units

- **Parts** (about 41% of FY2025 revenue ($241.6 million)): Aftermarket parts for B&W's and other manufacturers' boilers and environmental equipment at utilities and industrial plants, and a higher-margin part of the mix. 9M 2026 revenue was $185.2 million, flat year on year, but Q3 2026 brought record parts and services bookings as utilities reinvest in existing coal-fired plants.
- **Projects** (about 32% of FY2025 revenue ($186.9 million)): Engineered equipment and upgrades: package and waste heat boilers, natural gas conversions and environmental systems. From 2026 it includes the Base Electron data-center power project, which lifted 9M 2026 Projects revenue to $363.2 million from $128.0 million.
- **Construction** (about 27% of FY2025 revenue ($159.2 million)): Construction, maintenance and field services at customer plants. 9M 2026 revenue rose to $276.6 million from $115.7 million on large projects, but a skilled-labor shortage raised costs on one project, and the business is shifting toward variable-priced contracts.
- **BrightLoop and ClimateBright technologies**: Technology to produce steam or hydrogen from solid fuels while isolating CO2, alongside oxycombustion and post-combustion capture. A commercial-scale facility in Massillon, Ohio is due in late 2027, with material revenue expected in 2029.

## Strategic priorities

- **Data-center power generation**: B&W is designing and installing four 300-megawatt gas-fired plants for Base Electron in North Dakota under a contract worth up to $2.4 billion, with on-site work from early 2027 and commercial operation targeted for 2030; its data-center pipeline exceeds 6 gigawatts.
- **Enhanced combined cycle baseload**: B&W pitches 200 to 400 MW utility-grade units, boiler and steam turbine first and combustion turbine later, deliverable in 18 to 20 months, and reserved 1 gigawatt of Siemens Energy steam turbines (20 units of 50 MW).
- **Parts and services from coal plant reinvestment**: Utilities are refurbishing, recommissioning and running existing coal-fired plants longer, driving record parts and services bookings; the pipeline holds more than $10 billion of non-data-center power generation opportunities.
- **Adjusted EBITDA targets**: The FY2026 adjusted EBITDA target of $80.0 million to $105.0 million was reiterated and a first FY2027 target of $125 million to $140 million was set, about 75% covered by backlog or book-and-bill business.
- **BrightLoop commercialization**: The Massillon plant is planned for late 2027, with over $2 billion of BrightLoop opportunities outside the pipeline and bookings looked for in '28, '29 and '30.
- **Lower debt**: The 6.5% bonds due December 2026 were fully redeemed ($61.8 million), leaving secured debt and bonds of $166.4 million at September 30, 2026.

## Latest results

In Q3 2026 revenue was $290.8 million, up 109% from $139.2 million, including $77.8 million from Base Electron; nine-month revenue reached $824.9 million. Operating income was $13.8 million and adjusted EBITDA $17.7 million (+88%), while net income of $93.9 million was lifted by an $85.1 million non-cash gain on customer warrants; EPS was $0.61 against $0.30. Bookings were $228 million (+112%) and backlog $2.5 billion, with a pipeline above $16 billion. Gross margin was hurt by construction mix and a skilled-labor shortage on one project, and nine-month operating cash outflow was $130.3 million, mainly from a $152.9 million rise in trade receivables. Management reiterated the FY2026 adjusted EBITDA target of $80.0 million to $105.0 million and expects significant bookings in Q4 2026 and Q1 2027.

## Investments and deals

- **Divestitures to cut debt**: Vølund was sold in April 2025 (base price $15.0 million), Diamond Power in July 2025 ($177 million) and ASH in October 2025 ($29 million); business sale proceeds brought $216.3 million in 2025, and B&W Solar was abandoned.
- **Siemens Energy turbine reservation**: B&W reserved manufacturing rights for an additional 1 gigawatt of steam turbines (20 units of 50 MW), with first deliveries within 12 to 14 months of the Q2 2026 call.
- **BrightLoop facility in Massillon**: Capex went mainly to BrightLoop, with a commercial-scale facility under construction in Massillon, Ohio; 9M 2026 investing outflow was $14.8 million, mainly BrightLoop fixed assets.
- **Equity raises and buybacks**: A May 18, 2026 offering of 12.4 million shares raised $218.2 million net; a buyback of up to $50 million was authorised in July 2026, and $38 million of shares were repurchased in Q3.

## Challenges and risks

- **Skilled-labor shortage**: A nationwide shortage of boilermakers, welders, pipefitters and electricians raised construction costs and hurt productivity on one project ending in 2026; B&W uses union work, incentives and contract risk sharing.
- **Fixed-price contract risk**: Fixed-price contracts expose B&W to overruns from steel prices, tariffs, subcontractors and liquidated damages, and backlog can be cancelled or modified.
- **Cyclical customer spending**: Demand depends on capital and maintenance spending by power generators and steam-using industries, and cheap natural gas has shifted demand away from coal.
- **Pension and dilution**: Pension plans were underfunded by about $174.3 million at year-end 2025, and ATM programs and customer warrants dilute shareholders.
- **Cash tied in receivables**: Nine-month 2026 operating cash outflow was $130.3 million as receivables grew on larger projects; the CFO expects collections in Q4.

## What leadership says

> "Momentum in the data center market continues to build, with our pipeline now exceeding 6 gigawatts of opportunities." — Kenneth Young, Chairman and CEO, Third Quarter 2026 results press release, November 9, 2026

> "Rising global electricity demand is fueling increased needs from utilities, industrial and data center customers for our parts and services businesses and continues to drive new power generation opportunities." — Kenneth Young, Chairman and CEO, Third Quarter 2026 results press release, November 9, 2026

> "We don't see an end to the power generation demands coming from AI and data centers despite what the public markets have been stating." — Kenneth Young, Chairman and CEO, Q2 2026 earnings call, August 10, 2026

> "we expect Q4 to be a pretty decent amount of cash flow" — Cameron Frymyer, EVP and CFO, Q3 2026 earnings call, November 9, 2026


## Where a supplier can help

- **Skilled trades staffing and training**: Tied to the skilled-labor shortage: welder training, craft staffing, workforce scheduling and productivity tools ahead of Base Electron construction from early 2027.
- **Balance-of-plant and component supply**: Tied to the data-center power generation priority: suppliers of balance-of-plant equipment, electrical systems, condensers and fabricated components for four 300-megawatt plants and further enhanced combined cycle projects.
- **Project controls and cost management**: Tied to fixed-price contract risk and the shift to variable-priced construction: project controls, estimating and risk software that protect margins on large projects.
- **Receivables and working capital**: Tied to the cash tied in receivables: billing, collections and project financing services that shorten the cash cycle on large projects.
- **BrightLoop engineering partners**: Tied to BrightLoop commercialization: engineering, CO2 handling and hydrogen equipment partners for the Massillon facility and FEED studies.

_Tamtam's reading of the priorities and challenges above, not the company's own words._

## Key documents

### [Form 10-K for fiscal year 2025](https://www.sec.gov/Archives/edgar/data/1630805/000163080526000018/bw-20251231.htm)

Annual report · 2026-03-16

- Babcock & Wilcox is an Akron, Ohio energy technologies provider with nearly 160 years of history: steam generation equipment, aftermarket parts, construction and field services, and emissions control and carbon capture for utilities, industry and data centers.
- After divesting Vølund, Diamond Power, ASH and B&W Solar (abandoned) in 2025, plus BWRS, SPIG and GMAB in 2024, it now reports one segment, B&W.
- FY2025 revenue was $587.7 million: Parts $241.6 million, Projects $186.9 million, Construction $159.2 million. The United States accounted for $418.0 million and Canada for $90.6 million.
- Operating income was $20.7 million (2024: operating loss of $6.3 million). Adjusted EBITDA was $43.7 million (2024: $21.2 million). Loss from continuing operations narrowed to $32.8 million.
- Bookings were $549.6 million and year-end backlog was $423.6 million. The Base Electron agreement (Applied Digital-backed), signed February 26, 2026, covers four 300-megawatt gas-fired plants worth up to $2.4 billion and would take backlog to $2.8 billion.
- Balance sheet: cash and restricted cash $201.4 million, total debt $321.1 million, preferred stock $191.7 million. $84.8 million of 6.50% notes due 2026 had to be settled by November 30, 2026.
- BrightLoop (steam or hydrogen from solid fuels with CO2 isolated) is moving to commercialization, with a facility under construction in Massillon, Ohio.
- About 1,650 employees. Kenneth Young is Chairman and CEO, Cameron Frymyer CFO. B. Riley holds about 22.1% of the voting power.
- Main risks: fixed-price contract overruns, cyclical utility spending, bonding capacity, pension underfunding of about $174.3 million, and dilution from ATM programs and warrants.

### [Form 10-Q for the quarter ended September 30, 2026](https://www.sec.gov/Archives/edgar/data/1630805/000163080526000082/bw-20260930.htm)

Interim report · 2026-11-09

- Q3 2026 revenue was $290.8 million (Q3 2025: $139.2 million), including $77.8 million from Base Electron. Nine-month revenue was $824.9 million, including $209.5 million from Base Electron.
- Growth came from Projects ($123.0 million in Q3) and Construction ($108.8 million). Parts was flat at $59.0 million.
- Operating income was $13.8 million in Q3. Adjusted EBITDA was $17.7 million (Q3 2025: $9.4 million) and $55.5 million over nine months.
- An $85.1 million non-cash gain on customer warrants lifted Q3 income from continuing operations to $93.5 million.
- Backlog reached $2,510.0 million (2025: $374.0 million). Nine-month bookings were $2,890.9 million, of which $2.4 billion was Base Electron (four 300 MW gas plants for an AI factory, operation targeted 2030).
- A nationwide shortage of boilermakers and other skilled trades raised construction costs and hurt productivity.
- At September 30, 2026: cash $128.9 million and total debt $202.5 million. A May offering raised $218.2 million net, and 3.9 million shares were repurchased for $37.9 million.

### [Third Quarter 2026 Results press release](https://www.sec.gov/Archives/edgar/data/1630805/000163080526000080/e-2026q3earningsrelease.htm)

Interim report · 2026-11-09

- Q3 2026 revenue was $290.8 million (+109%). Net income was $93.9 million including the warrant revaluation; EPS $0.61 against $0.30.
- Adjusted EBITDA was $17.7 million (+88%). Adjusted net income was $4.8 million.
- Bookings were $228 million (+112%) and backlog $2.5 billion (+571%).
- The pipeline exceeds $16 billion, including 6 gigawatts of new incremental power for utilities, industrials and data centers.
- The FY2026 Adjusted EBITDA target of $80.0 million to $105.0 million was reiterated. A first FY2027 target was set at $125 million to $140 million.
- The 6.5% December 2026 bonds were fully redeemed ($61.8 million) and $38 million of shares were repurchased. Secured debt and bonds stood at $166.4 million.
- CEO Kenneth Young says the data-center pipeline now exceeds 6 gigawatts. The North Dakota project is on track, with county zoning and conditional-use approval secured.

### [Q3 2026 earnings call transcript](https://www.webull.com/news/15898213269434368)

Executive talk · Kenneth Young, Chairman and Chief Executive Officer · 2026-11-09

- Record parts and services bookings in Q3. Total bookings were over $228 million.
- The pipeline is above $16 billion, with more than $10 billion of non-data-center power generation and over $6 billion of data-center projects.
- Young expects significant bookings ($200 million, $300 million, $400 million and higher) in Q4 2026 and Q1 2027, many with utilities and manufacturers that want direct power.
- B&W pitches utility-grade "enhanced combined cycle" baseload units of 200 to 400 MW, deliverable in 18 to 20 months.
- North Dakota (Base Electron): permits are nearly complete. On-site work starts early 2027 and construction runs through 2029 into 2030.
- FY2027 Adjusted EBITDA target of $125 million to $140 million, called conservative. About 75% is covered by backlog or book-and-bill business.
- Labor shortages (welders, boilermakers, electricians) hit one construction project that ends this year. Mitigation: union work, incentives, contract risk transfer.
- BrightLoop: the Massillon plant is due late 2027, with over $2 billion of opportunities outside the pipeline. Material revenue is expected in 2029.

### [Q2 2026 earnings call transcript](https://www.fool.com/earnings/call-transcripts/2026/08/17/bw-bw-q2-2026-earnings-call-transcript/)

Executive talk · Kenneth Young, Chairman and Chief Executive Officer · 2026-08-10

- Q2 2026 revenue was $319.7 million (+130%), net income $14.3 million and adjusted EBITDA $21.8 million. The 2026 adjusted EBITDA target range was raised.
- H1 2026 bookings were $2.7 billion and backlog $2.6 billion. The pipeline is over $14 billion, including 4 to 6 gigawatts of generation opportunities.
- Base Electron is "ahead of expectations and on budget". On-site construction starts in the first part of 2027.
- Young expects a second data-center project at full notice to proceed this year. B&W reserved 1 gigawatt of Siemens Energy steam turbines (20 units of 50 MW).
- Enhanced combined cycle (boiler and steam turbine first, gas turbine later) offers power "3 to 5 years faster" than a combustion turbine alone, with a heat rate close to combined cycle.
- New coal: B&W is doing the TerraSpark FEED study and is in talks on other coal projects for data centers.
- Skilled-labor shortages raised costs on one project. Construction is shifting to variable-priced contracts.
- BrightLoop: Massillon is due in late 2027. Young looks for BrightLoop and ClimateBright bookings in '28, '29 and '30.

## Questions about Babcock & Wilcox

### What does Babcock & Wilcox do?

Babcock & Wilcox supplies boilers and steam generation systems, aftermarket parts, construction and field services, and emissions control and carbon capture technologies to utilities, industrial plants and data centers.

### What is Babcock & Wilcox's revenue?

FY2025 revenue from continuing operations was $587.7 million. Revenue for the nine months to September 30, 2026 was $824.9 million, including $209.5 million from Base Electron.

### How many employees does Babcock & Wilcox have?

About 1,650 employees at December 31, 2025.

### Who leads Babcock & Wilcox?

Kenneth Young is Chairman and CEO, and Cameron Frymyer is EVP and CFO.

### What is Babcock & Wilcox's strategy?

B&W is growing in power generation for utilities, industry and AI data centers, led by the Base Electron project, while expanding parts and services and commercializing BrightLoop. It targets FY2027 adjusted EBITDA of $125 million to $140 million.

_Written by Tamtam from the company's own published documents listed above, read in full. Figures are as those documents state them, for the periods they name. (2026-11-17)_