# TEPCO - Tokyo Electric Power Company account plan

> TEPCO Holdings is Japan's largest electricity group, serving about 45 million people in the Tokyo area, with ¥6,328.5 billion of FY2025 revenue.

## At a glance

TEPCO Holdings is a holding company whose four core operating companies cover the electricity value chain of the Tokyo metropolitan area: thermal power through its 50% of JERA, transmission and distribution, retail, and renewables; the holding company itself runs nuclear power and the Fukushima Daiichi decommissioning and compensation. Its grid area serves about 45 million people (about 37% of Japan's population) and about one third of national demand. In FY2025 (year to March 2026) revenue was ¥6,328.5 billion and ordinary profit ¥417.3 billion, but a ¥913.8 billion disaster loss for fuel-debris retrieval preparation produced a net loss of ¥454.2 billion. The group has 37,950 employees and pays no dividend.

## Business units

- **TEPCO Power Grid (transmission and distribution)** (19,838 employees, about 52% of group headcount; FY2025 revenue ¥2,294.3 billion): The regulated transmission and distribution operator for the Tokyo area, with 14,831 km of overhead and 7,032 km of underground lines. Data-center connection applications reached about 17.9 GW as of March 2026 and five substations (2,400 MVA) are being built or expanded. FY2025 ordinary profit was ¥81.7 billion; Q1 FY2026 swung to a loss of ¥31.2 billion on supply-demand adjustment costs. President Yoshinori Kaneko.
- **TEPCO Energy Partner (retail)** (FY2025 revenue ¥4,989.6 billion; 3,282 employees): Sells electricity, gas, equipment services, renewable PPAs and renewable menus to households and companies. It earned ¥254.9 billion of ordinary profit in FY2025, but retail volume is falling to competition and Q1 FY2026 showed an ordinary loss of ¥50.9 billion on higher procurement prices. President Momoko Nagasaki.
- **TEPCO Renewable Power** (1,618 employees): Runs the largest domestic hydro fleet and pumped storage, and develops offshore wind, geothermal, solar and green hydrogen under an asset-turnover model, plus overseas hydro. FY2025 ordinary profit was ¥40.3 billion. President Shinsuke Inoue.
- **TEPCO Fuel & Power (JERA stake)**: Holds TEPCO's 50% of JERA, which runs LNG procurement and thermal generation; Chubu Electric holds the other 50%. FY2025 ordinary profit was ¥83.3 billion. President Daisuke Sakai.
- **TEPCO Holdings (nuclear, Fukushima, corporate)** (13,212 employees): Runs Kashiwazaki-Kariwa, whose Unit 6 resumed commercial operation on 16 April 2026, the suspended Higashidori construction, Fukushima Daiichi decommissioning and compensation, the data-center one-stop offer, batteries, urban development and overseas projects.

## Strategic priorities

- **Reform of Fukushima decommissioning**: Under the Fifth Comprehensive Special Business Plan (approved 26 January 2026), decision rights move to the decommissioning entity as fuel-debris retrieval enters phase 3; about ¥500 billion a year must be secured for compensation and decommissioning.
- **Data-center growth with stable supply**: About 17.9 GW of data-center connection applications, a one-stop offer from site proposal to substation build, PPAs and CO2-free power through a dedicated AEI unit.
- **Immediate financial repair**: Stable Kashiwazaki-Kariwa operation, cost cuts of about ¥3.1 trillion over FY2025-FY2034, about ¥200 billion of asset sales, and stable positive free cash flow from FY2028.
- **Alliance with outside partners**: Partners bringing capital, technology and capabilities were solicited from February 2026; Chairman Keisuke Yokoo calls the alliance one core element of the equity story.
- **Decarbonisation**: Decarbonised sources above 60% of power delivered to customers by FY2040 (30.26% in FY2025) and net-zero CO2 from energy supply by 2050.
- **ROIC and FP&A management**: ROIC targets per business area, FP&A, ERP and shared databases so head office sees group-wide cash flows.

## Latest results

In Q1 FY2026 (April-June 2026) operating revenue rose 3.9% to ¥1,481.1 billion, but surging fuel and wholesale prices (crude at $112.7/bbl tentative versus $75.2) produced an operating loss of ¥34.2 billion and cut ordinary profit by ¥89.8 billion to ¥11.4 billion. Energy Partner and Power Grid both posted ordinary losses, while Holdings rose to ¥302.7 billion on dividend income. Kashiwazaki-Kariwa Unit 6 ran all quarter, generating 2.87 TWh. The net loss was ¥9.7 billion, against ¥857.6 billion a year earlier, and the FY2026 forecast remains "to be determined".

## Investments and deals

- **Grid build-out for data centers**: Grid investment for data centers and renewables is the main capex driver; FY2025 capex was ¥904.8 billion.
- **Asset sales and asset turnover**: About ¥200 billion of asset sales in principle within three years, after FY2025 sales of KANDENKO shares (¥103.0 billion gain) and the SoloTime shared-office business; renewables develop projects and sell stakes to partners.
- **Renewables and hydrogen**: ¥180 billion of green bonds issued over FY2021-FY2025, a 16 MW Power-to-Gas demonstration started in October 2025, and an offshore wind project off Saikai, Nagasaki.
- **Nuclear restart and Niigata contribution**: Unit 7's Specialized Safety Facility completion is targeted for August 2029; TEPCO agreed a contribution of about ¥100 billion to Niigata Prefecture, with ¥10.0 billion in FY2026.
- **Grid batteries**: A grid battery alliance with Daiwa House signed on 22 June 2026, adding to more than 100 NAS battery sites.

## Challenges and risks

- **Fuel and wholesale price exposure**: Middle East tension including the Strait of Hormuz, and the end of the long-term purchase contract with JERA, raise exposure to market prices; Tokyo-area spot prices hit ¥40/kWh or more in 107 half-hour periods in Q1 FY2026.
- **Fukushima costs**: Decommissioning costs are now seen at about ¥5.5 trillion and total Fukushima funding needs at ¥23.4 trillion.
- **Weak balance sheet and cash flow**: Free cash flow was -¥103.2 billion in FY2025, the eighth consecutive deficit; equity ratio 21.8% and interest-bearing debt ¥6,633.7 billion; no dividend.
- **Retail competition**: Retail volume fell 15.2 TWh in FY2025, mostly to competition.
- **Rising capex and interest rates**: Inflation, labour costs and higher interest rates lengthen payback under the revenue-cap regime; Niigata residents remain uneasy about TEPCO running the plant.

## What leadership says

> "not a goal but a starting line" — Tomoaki Kobayakawa, President, On the Kashiwazaki-Kariwa Unit 6 restart, Integrated Report 2026, 30 September 2026 (translated)

> "a great responsibility and also a growth opportunity" — Tomoaki Kobayakawa, President, On generative AI and data-center demand, Integrated Report 2026, 30 September 2026 (translated)

> "if corporate value does not rise, there was no point in my coming" — Keisuke Yokoo, Chairman, Chairman's message, Integrated Report 2026, 30 September 2026 (translated)

> "It is hard to keep being chosen on price alone." — Hiroyuki Yamaguchi, Representative Executive Vice President and CFO, Directors' dialogue, Integrated Report 2026, 30 September 2026 (translated)


## Where a supplier can help

- **Substation and grid equipment for data centers**: Data-center connection applications and the five substations being built or expanded create demand for transformers, switchgear, cables and grid engineering capacity.
- **Cost reduction and procurement efficiency**: The ¥3.1 trillion cost-reduction target over FY2025-FY2034 favours suppliers that can show measurable savings in operations, maintenance and procurement.
- **FP&A, ERP and data platforms**: The FP&A rollout, phased ERP and shared databases and ROIC management are openings for finance software, data integration and consulting.
- **Retail energy services and pricing**: Facing retail competition and price swings, Energy Partner needs tariff design, energy-trading, customer-retention and carbon-tracking tools to sell more than price.
- **Batteries, renewables and hydrogen partners**: Grid batteries, offshore wind, geothermal and Power-to-Gas projects under the asset-turnover model look for equipment suppliers, EPC contractors and co-investors.

_Tamtam's reading of the priorities and challenges above, not the company's own words._

## Key documents

### [TEPCO Integrated Report 2026 (FY2025, Japanese edition)](https://www.tepco.co.jp/about/ir/library/annual_report/pdf/202609tougou-j.pdf)

Annual report · 2026-09-30

- TEPCO Holdings is Japan's largest electricity group: its Power Grid area serves about 45 million people (about 37% of Japan's population) and about one third of national power demand (268.3 TWh); consolidated revenue about ¥6.3 trillion, total assets about ¥15.5 trillion, 37,950 employees (FY2025, year to March 2026).
- FY2025: revenue ¥6,328.5 billion, ordinary profit ¥417.3 billion (+¥162.8 billion, mainly fuel-cost-adjustment timing), but a net loss of ¥454.2 billion after a ¥913.8 billion extraordinary disaster loss for Fukushima Daiichi fuel-debris retrieval preparation; free cash flow -¥103.2 billion, the eighth consecutive deficit; equity ratio down 3.3 points to 21.8%; no dividend (distributable amount negative).
- Kashiwazaki-Kariwa Unit 6 resumed commercial operation on 16 April 2026, the first in 14 years; one unit improves earnings by about ¥100 billion a year, and the CFO puts the Q1 FY2026 effect at about ¥47 billion; the President wants Unit 7 restarted as early as possible, provided it can be done safely.
- The Fifth Comprehensive Special Business Plan (January 2026) sets four priorities: reform of decommissioning, stable supply plus growth (data centers), immediate financial repair (KK operation, cost cuts of about ¥3.1 trillion over FY2025-34, about ¥200 billion of asset sales) and an alliance: partners were solicited from February 2026 and proposals are being examined.
- Data centers are the growth story: about 17.9 GW of data-center connection applications in the Power Grid area as of March 2026; five substations (2,400 MVA) being built or expanded; one-stop offer from site proposal to substation build, PPAs and CO2-free power via a dedicated AEI (Area Energy Innovation) unit.
- Targets: stable positive free cash flow from FY2028; decarbonised sources above 60% of power delivered to customers by FY2040 (30.26% in FY2025); about ¥500 billion a year secured for Fukushima compensation and decommissioning.
- New chairman Keisuke Yokoo, a finance and investment veteran, joined in June 2026 to build an "equity story" around the alliance; four core operating companies: Fuel & Power (JERA stake), Power Grid, Energy Partner (retail), Renewable Power.
- Risks: fuel and wholesale price swings (Middle East, Strait of Hormuz), more market exposure after the JERA long-term purchase contract ended in FY2026, rising capex and interest rates, nuclear trust in Niigata, and Fukushima decommissioning costs now seen at about ¥5.5 trillion.

### [FY2025 Financial Results presentation (April 2025 - March 2026)](https://www.tepco.co.jp/en/hd/about/ir/library/presentations/pdf/260430_01-e.pdf)

Interim report · 2026-04-30

- FY2025 (April 2025-March 2026): operating revenue ¥6,328.5 billion (-¥481.8 billion, 92.9%), operating profit ¥337.6 billion, ordinary profit ¥417.3 billion (+¥162.8 billion), net loss attributable to owners ¥454.2 billion (FY2024: profit ¥161.2 billion).
- Revenue fell with total electricity sales volume (213.2 TWh, -15.4 TWh); retail volume down 15.2 TWh, mostly competition (-14.4 TWh at EP).
- Profit rose on a positive turn in fuel-cost-adjustment timing differences and efficiency gains; extraordinary losses of ¥996.6 billion, including ¥913.8 billion on disaster (¥903.0 billion of new Fukushima fuel-debris preparation costs).
- By company: Energy Partner ordinary profit ¥254.9 billion, HD ¥128.9 billion (dividend income), Fuel & Power ¥83.3 billion, Power Grid ¥81.7 billion, Renewable Power ¥40.3 billion.
- Equity ratio fell 3.3 points to 21.8%; interest-bearing debt ¥6,633.7 billion; operating cash flow ¥560.3 billion, investing -¥663.6 billion.
- No FY2025 year-end dividend and none planned for FY2026; FY2026 forecast "to be determined".
- Kashiwazaki-Kariwa Unit 6 resumed commercial operation on 16 April 2026; Unit 6's anti-terrorism facility deadline expected to move to April 2031.
- Fifth Comprehensive Special Business Plan approved on 26 January 2026; Fukushima funding outlook unchanged at ¥23.4 trillion; compensation paid to date ¥11,682.7 billion.

### [FY2026 1st Quarter Financial Results presentation (April - June 2026)](https://www.tepco.co.jp/en/hd/about/ir/library/presentations/pdf/260729_01-e.pdf)

Interim report · 2026-07-29

- Q1 FY2026 (April-June 2026): operating revenue ¥1,481.1 billion (+3.9%), operating loss ¥34.2 billion (Q1 FY2025: profit ¥64.6 billion), ordinary profit ¥11.4 billion (-¥89.8 billion), net loss ¥9.7 billion (versus -¥857.6 billion a year earlier, which carried a ¥903.0 billion disaster loss).
- The squeeze came from surging fuel and wholesale market prices: crude at $112.7/bbl (tentative) versus $75.2 and the yen at 159.6/$; Tokyo-area spot prices hit ¥40/kWh or more in 107 half-hour periods.
- Energy Partner swung to an ordinary loss of ¥50.9 billion (-¥81.5 billion) on lower volume and higher procurement prices; Power Grid to a loss of ¥31.2 billion on supply-demand adjustment costs.
- Holdings' ordinary profit rose to ¥302.7 billion on dividend income; Fuel & Power ¥56.6 billion; Renewable Power ¥28.1 billion.
- Kashiwazaki-Kariwa Unit 6 ran all quarter: nuclear generation 2.87 TWh and a nuclear utilisation ratio of 17.1%.
- Total electricity sales 44.1 TWh (-8.4%), retail 34.4 TWh (-11%), area demand 57.8 TWh.
- FY2026 forecast still "to be determined"; equity ratio 22.1%; interest-bearing debt ¥6,745.2 billion.
- TEPCO agreed to contribute about ¥100 billion to Niigata Prefecture (¥10.0 billion in FY2026).

### [Directors' dialogue: CFO Hiroyuki Yamaguchi and outside director Takakazu Uchida (Integrated Report 2026, Corporate Governance section)](https://www.tepco.co.jp/about/ir/library/annual_report/pdf/202609tougou06-j.pdf)

Executive talk · Hiroyuki Yamaguchi, Representative Executive Vice President and CFO · 2026-09-30

- A directors' dialogue in the 2026 integrated report between CFO Hiroyuki Yamaguchi and outside director Takakazu Uchida, former CFO of Mitsui & Co., on capital discipline, cash flow and people at TEPCO.
- Yamaguchi wants investment in "human value" alongside assets, and a "corporate value tree" so every site sees how its work drives company-wide profit and value.
- FP&A is being rolled out to link field operations to the numbers; ERP and shared databases are phased in so head office and operating companies work from the same data.
- With finances tight, HD needs a group-wide view of cash flows while respecting the core operating companies' autonomy; Yamaguchi calls information sharing his responsibility as CFO.
- Uchida pushes "bad news first" for finance: early warning signs from the field, before numbers are revised, must reach management.
- On cash flow, Uchida says to look at operating cash flow as the measure of the core business, and to check that investments earn more than the cost of capital without starving future opportunities.
- Both see a public-service culture that is wary of profit; in liberalised retail TEPCO must create value customers choose, as price alone will not keep them.
- Uchida rates the board as frank and active and wants more time on "where TEPCO is heading".

## Questions about TEPCO - Tokyo Electric Power Company

### What does TEPCO do?

TEPCO Holdings generates, transmits and sells electricity and gas for the Tokyo metropolitan area through four core operating companies, runs nuclear plants and is responsible for Fukushima Daiichi decommissioning and compensation.

### What is TEPCO's revenue?

Consolidated revenue was ¥6,328.5 billion in FY2025 (year to March 2026), with ordinary profit of ¥417.3 billion and a net loss of ¥454.2 billion.

### How many employees does TEPCO have?

37,950 employees, of whom 19,838 work at TEPCO Power Grid.

### What is TEPCO's strategy?

The Fifth Comprehensive Special Business Plan of January 2026 sets four priorities: reform of decommissioning, stable supply plus growth from data centers, immediate financial repair, and an alliance with outside partners.

### Who leads TEPCO?

Tomoaki Kobayakawa is President, Keisuke Yokoo became Chairman in June 2026, and Hiroyuki Yamaguchi is CFO.

_Written by Tamtam from the company's own published documents listed above, read in full. Figures are as those documents state them, for the periods they name. (2026-11-17)_