Elecnor is a Spanish infrastructure, energy and services group in more than 40 countries, with EUR 4,387.3 million of 2025 sales and 28,263 people.

Grupo Elecnor, founded in 1958, is a Spanish group that builds and maintains electricity, renewable-energy, telecom, rail, water and building infrastructure and invests in transmission and renewable assets through Celeo. It works mainly B2B for utilities, telecom operators, public administrations, infrastructure investors and asset owners, in more than 40 countries; Spain plus Brazil, the United States, Australia, Italy, the Dominican Republic, Chile and Angola make up 88% of sales. In FY2025 consolidated sales were EUR 4,387.3 million (+15%), EBITDA EUR 267.8 million and attributable net profit EUR 110.7 million, with a team of 28,263 people at year-end. The parent Elecnor, S.A. is listed, and Cantiles XXI, S.L. holds 52.8%.

Business units

Strategic priorities

Margin over volume
The Strategic Plan 2025-2027 targets sales of about EUR 4 billion a year and net profit above EUR 100 million a year; the CEO says the group does not sacrifice profitability for volume and wants Projects margins to exceed those of Services.
Cash and shareholder returns
Free cash flow of at least EUR 350 million over 2025-2027, cash conversion above 1x and more than EUR 220 million of dividends over the plan, double the 2021-2023 dividends.
Investment platform
Aim to commit up to EUR 400 million in transmission, renewables, energy efficiency, digital infrastructure and data centres, keeping net debt/EBITDA below 1.5x.
United States expansion
The US is a priority market with three subsidiaries; Texas (Austin, San Antonio, Dallas) is named a high-performing market, with small acquisitions possible to enter new regions.
Grid, storage and electrification
2026 regional priorities include grid stability, storage and system resilience in Europe, and transmission, renewables and storage in Oceania and Latin America.
Digital transformation
AI, robotics and data analytics are one of the plan's six levers, alongside cybersecurity and innovation.

Latest results

For January-September 2026, revenue was EUR 3,143.2 million (-0.2%), with domestic sales up 18.1% and international sales down 13.2%. EBITDA rose 16.4% to EUR 215.8 million and attributable net profit 27.3% to EUR 102.9 million (EUR 80.8 million a year earlier). Services grew turnover 14.0%, while Projects turnover fell 15.7% but its EBITDA margin rose to 10.0% from 6.1%. The 12-month executable backlog stood at EUR 2,990.5 million (+5.1% vs end-2025), 68.8% international. Management says it is on track with the 2025-2027 Strategic Plan and keeps the commitment to exceed EUR 220 million of dividends over the plan.

Investments and deals

US and Spanish own projects
In 2026 construction began on a wind project in Aragon and three photovoltaic projects in the United States, an investment commitment close to EUR 100 million.
Acquisitions
Jet Aircraft Services (JAS), a Spanish aircraft maintenance company, was acquired as an entry into aircraft maintenance, and Adventum's telecom business in July 2025.
Disposals of development companies
The development subsidiaries Moana Data and Eternelle Energie were sold in 2026.
Sustainable financing
A EUR 350 million sustainable syndicated loan maturing June 2030 and a MARF promissory note programme of up to EUR 400 million; more than 80% of financing limits are classified as sustainable.

Challenges and risks

Skilled labour scarcity
Rising absenteeism and scarcity of qualified technical labour affect planning and productivity; growth in the US is controlled because of access to skilled labour.
International project revenue decline
International sales fell 13.2% in 9M 2026 as large international projects reached advanced stages.
Permitting and curtailment in Latin America
The Chile country manager warns that permitting delays and curtailment can undermine project financial viability, and that grids able to absorb renewable output are lagging.
Cost inflation and renewables pressure
Construction faces structural inflation, and renewables carry regulatory complexity and cost pressure.
Safety scrutiny
The 2026 rail accidents in Spain put infrastructure safety under scrutiny; health and safety is named among the group's ESG risks.

What leadership says

“we do not sacrifice profitability for volume”

Alberto García de los Ángeles, CEO · Capital Markets Day, 11 September 2025 (translated from Spanish)

“In Chile, we are currently building a nearly 300 MW solar photovoltaic plant with its corresponding BESS, and we are participating in several tenders totalling more than 500 MW, also incorporating battery systems”

Jaime Bengoa, Country Manager Chile · Future Energy Summit Southern Cone, reported by Energía Estratégica on 22 January 2026

“We adapt to what the market brings, but the healthiest approach is for everything to move forward together”

Jaime Bengoa, Country Manager Chile · Future Energy Summit Southern Cone, reported by Energía Estratégica on 22 January 2026

Where a supplier can help

Field workforce productivity
Skilled labour scarcity and the digital transformation lever point to field-service, workforce planning and robotics tools that let the same crews do more.
Grid and storage equipment
Priorities in grid stability, storage and transmission, plus BESS and hybrid projects in Chile and Australia, create demand for transformers, battery systems and substation equipment.
US growth support
The US expansion priority, with new PV projects and possible small acquisitions, fits recruiting, local subcontracting and equipment suppliers in Texas and other regions.
Project margin control
The aim of higher Projects margins favours project controls, procurement and risk-management tools that limit penalties and overruns.
Data-centre and digital infrastructure build
The investment platform's focus on data centres and digital infrastructure opens room for suppliers of electrical, cooling and building systems.

Tamtam's reading of the priorities and challenges above, not the company's own words.

Selling to companies like Elecnor Group?

Tamtam finds the companies that match your ideal customer, researches each account and tells you who to contact and when.

Find similar companies

Key documents

Read in full by Tamtam; each summary links to the document itself.

Questions about Elecnor Group

What does Elecnor do?

Elecnor builds, maintains and services electricity, renewable, telecom, rail, water and building infrastructure for utilities, telecom operators and public bodies, and invests in transmission lines and renewable assets through Celeo.

What is Elecnor's revenue?

Consolidated sales were EUR 4,387.3 million in FY2025 (+15%). For January-September 2026, revenue was EUR 3,143.2 million (-0.2%).

How many people work at Elecnor?

The team was 28,263 people at the end of 2025, and headcount was 29,704 at 30 June 2026.

Who leads Elecnor?

Alberto García de los Ángeles has been CEO since 1 January 2025, and Jaime Real de Asúa is non-executive chairman.

What is Elecnor's strategy?

The Strategic Plan 2025-2027 favours margin over volume, targets net profit above EUR 100 million a year and more than EUR 220 million of dividends, and aims to commit up to EUR 400 million of investments.

Written by Tamtam from the company's own published documents listed above, read in full. Figures are as those documents state them, for the periods they name. (2026-11-17)