Salt River Project account plan

Water and power utility

At a glance

Salt River Project is a not-for-profit water and power utility serving more than 2 million people in central Arizona, with $4.7 billion of FY26 revenue.

Salt River Project (SRP) is a community-based, not-for-profit water and energy utility founded in 1903 that serves more than 2 million people in central Arizona. It combines an electric system (the Salt River Project Agricultural Improvement and Power District, with a 2,900-square-mile service territory) and an irrigation system run by the Salt River Valley Water Users' Association. In the fiscal year ended April 30, 2026 (FY26) it reported operating revenues of $4.7 billion and net revenues of $430.9 million, with 1,199,621 customer accounts and 5,878 employees at year-end. It has no investors; a publicly elected Board of Directors sets prices and acts as regulator, and its bonds are rated AA+ (S&P) and Aa1 (Moody's).

Business units

Strategic priorities

Doubling generation resources by 2035
SRP plans to at least double generation resources by 2035, after a record system peak of 9,072 MW on July 24, 2026, above the 8,542 MW record of August 2025.
Serving large loads without shifting costs
Under the Large Customer Integration Process (introduced 2025) and the updated E-67 Price Plan, customers with at least 20 MW of forecast load pay for their upgrades upfront and face minimum billing tied to actual use or 80% of forecast demand.
Renewables and storage build-out
Nearly 2,300 MW of solar, storage and hybrid agreements from the 2023-24 RFP cycles, a NextEra agreement for up to 3,000 MW more utility-scale solar, and a 600 MW SunZia Wind PPA with Pattern Energy (400 MW from fall 2026, 600 MW by summer 2027).
Customer systems modernization
The Customer Modernization Program, which replaces legacy customer systems with a new SRP Energy My Account portal and mobile app, is on track for a March 2027 launch.
Enterprise AI
SRP launched its first enterprise-wide AI strategy and an AI Hub in FY26, with Arizona State University training leaders on AI.
Keeping rates low
Rates are about 37% below the regional average and, per the CEO, on average 18% below other major Arizona utilities; a net 2.4% increase took effect November 1, 2025.

Latest results

In the first quarter of FY27 (May 1 to July 31, 2026), operating revenues were $1,549.6 million against $1,454.2 million a year earlier, with retail electric revenues up $94.6 million (+7.2%) on higher commercial sales and the November 2025 rate increases. Wholesale revenues fell 17.2% to $85.6 million. Operating expenses dropped 13.8% to $913.6 million because of a $195.5 million fair value gain; excluding fair value effects they rose 5.3% on power purchases and O&M. Net revenues were $550.9 million vs $482.0 million ($404.9 million vs $371.7 million excluding fair value effects). Customers reached 1,201,604 (+1.3%), and debt service coverage was 3.93 with a debt ratio of 45.1% for the 12 months to July 31, 2026.

Investments and deals

FY26 capital programme
Capital expenditures of $2,160.3 million in FY26: generation 39% (Coolidge Expansion, Pumped Storage, Palo Verde, Mesquite), distribution 30% (a third for new business) and transmission 13%.
New capacity online
Nearly 800 MW of nameplate capacity came online over the past year: Copper Crossing Solar (55 MW, SRP's first utility-owned solar), Flatland Energy Storage, the Pediment Battery Energy Storage System (250 MW/1,000 MWh with Aypa Power) and parts of the Coolidge Expansion Project.
Gas conversion and pumped storage
Approvals secured to convert Coronado Generating Station from coal to natural gas; the Pumped Storage Project is at 60% design completion; Marigold and SunDog energy centers are underway.
Long-duration storage and nuclear study
A 19 MW, 10-hour CO2 battery with Energy Dome at Coronado expected in 2029, part of a collaboration with Google; a preliminary new-nuclear siting study with APS and TEP, with no decision taken and no technology chosen.
Bond financing
$727.7 million of 2025 Series C Electric System Revenue Bonds issued in November 2025 at a 4.7% average effective rate, with $5.9 billion of further revenue bond authorization remaining.

Challenges and risks

Record and fast-rising demand
Peak demand reached 9,072 MW in July 2026, and a load study of 24 proposed large-load projects represented about 7.2 GW and an estimated $12.8 billion of transmission investment.
Margin pressure in FY26
Operating expenses rose 12.8% to $4.5 billion on purchased power under renewable contracts, outage maintenance and depreciation; net revenues fell to $430.9 million from $604.0 million and cash from operations to $873.3 million.
Environmental regulation
EPA rules on greenhouse gases, mercury, regional haze, ozone and coal combustion residuals; Coronado's wet impoundment is usable until September 30, 2026, with alternate disposal estimated at $82 million.
Water and wildfire risk
The Gila River water-rights adjudication pending since 1974, Colorado River conditions, PFAS regulation, and wildfire, addressed with fire weather forecasting and a Public Safety Power Shutoff program.
Public debate on data centers
The CEO wrote to answer confusion about whether data center growth affects reliability and affordability; data centers' estimated 2025 peak demand was 441 MW, 5.1% of SRP's 8,542 MW peak.

What leadership says

“These market and policy factors — not utility decisions — drive data center growth”

Jim Pratt, General Manager and Chief Executive Officer · Guest commentary "The facts about SRP and data centers", Arizona Capitol Times, March 31, 2026

“a growing but still manageable share of our total electric usage”

Jim Pratt, General Manager and Chief Executive Officer · On data centers' share of peak demand, Arizona Capitol Times, March 31, 2026

“ensure new data centers in our service territory do not raise electric rates for residential customers”

Jim Pratt, General Manager and Chief Executive Officer · Arizona Capitol Times guest commentary, March 31, 2026

Where a supplier can help

Generation and storage delivery
The plan to at least double generation resources by 2035 and the Coolidge Expansion, Pumped Storage and Coronado conversion projects create demand for engineering, construction, equipment and project-controls partners.
Grid and large-load interconnection
The Large Customer Integration Process and the transmission build behind large loads call for study tools, substation and transmission equipment, and cost-estimating support.
Customer platform and AI
The Customer Modernization Program (March 2027 launch) and the new enterprise AI strategy and AI Hub open room for software, data, change management and training suppliers.
Environmental compliance
Coal combustion residual disposal at Coronado ($82 million estimate) and EPA air rules point to environmental engineering and compliance services.
Wildfire and water resilience
The wildfire risk and the fuel-moisture sensor pilot, plus water infrastructure such as the Gilbert Road Pipeline and new wells, suggest openings for monitoring, sensing and water infrastructure suppliers.

Tamtam's reading of the priorities and challenges above, not the company's own words.

Selling to companies like Salt River Project?

Tamtam finds the companies that match your ideal customer, researches each account and tells you who to contact and when.

Find similar companies

Key documents

Read in full by Tamtam; each summary links to the document itself.

Questions about Salt River Project

What does Salt River Project do?

SRP is a not-for-profit utility providing electricity and water to more than 2 million people in central Arizona. Its electric system generates, buys, transmits and distributes power in a 2,900-square-mile territory, and its water arm delivers Salt and Verde river water and groundwater.

How large is SRP's revenue?

SRP reported operating revenues of $4.7 billion and net revenues of $430.9 million for the fiscal year ended April 30, 2026. In the first quarter of FY27 (May to July 2026) operating revenues were $1,549.6 million.

How many employees does SRP have?

SRP had 5,878 employees at the end of FY26 (April 30, 2026), serving 1,199,621 customer accounts.

What is SRP's strategy?

SRP plans to at least double generation resources by 2035 through gas, solar, wind and storage additions, while making large customers above 20 MW pay for their own upgrades so costs are not shifted to residential customers.

Who leads SRP?

Jim Pratt is General Manager & CEO, and Chris Dobson is President of the elected Board. The executive team includes Brian J. Koch (Chief Financial Executive) and Bobby Olsen (Chief Power System Executive).

Written by Tamtam from the company's own published documents listed above, read in full. Figures are as those documents state them, for the periods they name. (2026-11-17)