SSE plc account plan

Investing in clean energy

At a glance

SSE plc is a UK-listed electricity networks, renewables and flexible generation group with 15,197 direct employees and a £33bn investment plan to 2029/30.

SSE plc invests in, builds and operates electricity infrastructure in the UK, Ireland and selected overseas markets: transmission and distribution networks, onshore and offshore wind, hydro and batteries, flexible gas-fired generation, and energy supply to homes and businesses. It is organised in three pillars, Networks, Renewables and Flexibility, and serves 4.96m networks and supply customers. In the year to 31 March 2026 it reported revenue of £10,186.5m and adjusted operating profit of £2,236.6m (£2,419.2m the year before), with 15,197 direct employees. It is listed in the UK, with a market capitalisation of £31bn at 31 March 2026. Martin Pibworth is Chief Executive, Barry O'Regan CFO and Sir John Manzoni Chair.

Business units

Strategic priorities

£33bn investment plan to 2029/30
A fully-funded plan announced in November 2025 trebles investment over five years, with about 80% (~£27bn) in regulated networks and ~20% (~£6bn) in Renewables and Flexibility.
North of Scotland transmission build-out
About £22bn goes to SSEN Transmission, taking gross RAV to ~£30bn by 2029/30 (~30% CAGR) across 11 major projects (six onshore, five offshore); 25 of 34 major consents were secured at the annual report.
Earnings and dividend targets
Adjusted EPS of 168-193p for 2026/27 and 225-250p for 2029/30, a 10-13% CAGR from 2025/26; dividend growth of 5-10% a year from a 64.2p baseline; ~80% of EBITDA index-linked in 2029/30.
Renewables capacity to ~9GW
Installed capacity is to reach ~9GW by 2029/30 through Dogger Bank, Berwick Bank (phase B won a 20-year CfD for 1.4GW, FID expected in 2027) and battery projects, under a 'value over volume' discipline.
Cost efficiency
The Operating Model and Efficiency Review targets over £100m of savings during FY27 and over £200m recurring by the end of FY28.
Balance sheet discipline
Net debt/EBITDA is to stay below 4.5x through the plan (3.3x at March 2026), funded by a £2bn equity placing, rising debt and hybrids and around £2bn of asset rotations.

Latest results

In FY2025/26 (year to 31 March 2026) adjusted operating profit was £2,236.6m against £2,419.2m, adjusted EPS fell 5% to 153.5p on the dilution from the November 2025 equity issue, and the full-year dividend rose 7% to 68.7p. Capex reached a record £3,585.6m. In its trading update of 1 October 2026, ahead of H1 2026/27 results on 18 November 2026, SSE said adjusted investment in networks was around 70% higher than a year earlier and renewable output around 20% higher. It expects interim adjusted EPS of 64 to 68 pence, half-year capital investment of around £2.5bn and adjusted net debt and hybrid capital of around £11.5bn. Full-year guidance is unchanged: adjusted EPS of 168-193p for 2026/27 and capex of over £5bn.

Investments and deals

Record capex
Adjusted investment and capex was a record £3,585.6m in FY2025/26 (£2,910.4m the year before) and is expected at over £5bn in 2026/27.
Spittal-Peterhead and EGL2
SSE's largest ever contract, €2bn with NKT, covers the Spittal-Peterhead HVDC link; EGL2, a 2GW, 505km HVDC link with National Grid, opens in 2029.
Dogger Bank and Berwick Bank
Dogger Bank (3.6GW, SSE 40%) has turbine installation complete at A and beyond the half-way point at B as of October 2026; Berwick Bank is consented for up to 4.1GW.
New thermal and battery capacity
Tarbert Next Generation (300MW, from October 2027) and Platin (170MW, from October 2028) in Ireland; Monk Fryston (320MW), Fiddlers Ferry (150MW) and Derrymeen (100MW) batteries under construction.
Equity placing and asset rotation
A £2bn equity placing completed in November 2025, with around £2bn of targeted asset rotations timed mainly towards the end of the plan.

Challenges and risks

Energy affordability
Rated as slightly increased: consumer energy debt rose 20% over 2025 and the Electricity Generator Levy went up from 45% to 55%.
Political and regulatory change
Remains heightened amid fragmented net zero sentiment, and was reassessed after the conflict in the Middle East.
Large capital projects and supply chain
Large Capital Projects Management and Supply Chain are rated high likelihood and high impact as the plan trebles investment.
Grid delays on onshore wind
A £155.8m impairment was taken on the Aberarder and Strathy South onshore wind farms, delayed by grid access.
Cyber security and resilience
Rated high likelihood and high impact, alongside storm exposure such as Storm Floris, which affected almost 85,000 distribution customers.

What leadership says

“Right now, the most critical piece in the energy transition jigsaw is the transmission network in the north of Scotland.”

Martin Pibworth, Chief Executive · SSE plc Annual Report 2026, June 2026

“This is a great growth opportunity, but it is not incorporated in our targets.”

Martin Pibworth, Chief Executive · On data centres, full-year results presentation, 28 May 2026

“Ultimately, these vital projects are in our licence conditions and they will be delivered.”

Martin Pibworth, Chief Executive · On transmission projects, HY26 interim results and 2030 plan presentation, November 2025

“We don't take issuing equity lightly”

Barry O'Regan, CFO · HY26 interim results and 2030 plan presentation, November 2025

Where a supplier can help

Transmission project delivery
Tied to the north of Scotland transmission build-out and the large capital projects risk: suppliers of engineering, modular substations, construction services and project controls can support 11 major projects.
Efficiency programme
Tied to the over £200m recurring savings target by the end of FY28: automation, procurement and operating-model tools that help a more commercially-minded organisation.
Data centre connections
Tied to the data centre growth option outside targets: partners for private network connections, power supply and energy services to hyperscalers in Ireland and the M4 corridor.
Cyber and grid resilience
Tied to the cyber security and storm resilience risks: security, monitoring and network restoration solutions across transmission and distribution.
Battery and thermal build
Tied to the battery and Irish thermal investments: equipment, EPC and commissioning services for projects under construction.

Tamtam's reading of the priorities and challenges above, not the company's own words.

Selling to companies like SSE plc?

Tamtam finds the companies that match your ideal customer, researches each account and tells you who to contact and when.

Find similar companies

Key documents

Read in full by Tamtam; each summary links to the document itself.

Questions about SSE plc

What does SSE plc do?

SSE builds and operates electricity transmission and distribution networks, renewable generation (wind, hydro, batteries), flexible gas-fired generation and energy supply in the UK, Ireland and selected overseas markets.

What is SSE's revenue?

Reported revenue was £10,186.5m in the year to 31 March 2026, with adjusted operating profit of £2,236.6m.

How many employees does SSE have?

SSE had 15,197 direct employees, around 15,000 people, as of its 2026 annual report.

What is SSE's strategy?

A fully-funded £33bn five-year investment plan to 2029/30, about 80% in regulated networks, targeting adjusted EPS of 225-250p in 2029/30 and ~9GW of renewables capacity.

Who leads SSE?

Martin Pibworth is Chief Executive, Barry O'Regan is CFO and Sir John Manzoni is Chair.

Written by Tamtam from the company's own published documents listed above, read in full. Figures are as those documents state them, for the periods they name. (2026-11-17)