Supplying reliable energy networks

At a glance

Stedin is a publicly owned Dutch electricity and gas grid operator serving about 5.6 million people, with €2,300 million of 2025 revenue.

Stedin Group builds, operates and maintains electricity and gas distribution networks in most of South Holland, Utrecht and Zeeland, an area with approximately 5.6 million people that includes the Rotterdam and Zeeland port and industrial areas. It is a semi-public company owned by 61 municipalities, two provinces and the State of the Netherlands; Rotterdam is the largest shareholder at approximately 27.9%, and its bonds are listed on Euronext Amsterdam. In FY2025 revenue was €2,300 million (+€252 million), operating profit €449 million and profit after tax €278 million. The workforce grew by 555 FTE to 6,787 FTE at the end of 2025.

Business units

Strategic priorities

Build grid capacity faster
Investment targets of €1,657 million for 2026 and €2,500-3,000 million by 2030, with added capacity rising from an 858 MVA target in 2026 to around 1,500 MVA a year by 2030.
Flexibility and congestion management
Contracted effective flexible capacity reached 367 MW in H1 2026 against a 600 MW target for 2026 and 1,300-1,500 for 2030, using Congestion Service Providers, batteries and the Utrecht Flextender.
Neighbourhood approach
Approximately 3,000 neighbourhoods are to be reinforced by 2050, with capacity being built to upgrade more than 200 neighbourhoods a year.
Digitalisation and AI for productivity
41% of medium-voltage substations were digitally metered in H1 2026 (target 56% for 2026, over 80% ultimately), and the H1 2026 strategy update adds targeted digitalisation and AI to raise productivity.
Modular, prefabricated construction
Plug-and-play, prefabricated building becomes the standard approach, alongside standard transformer types and a plug-in medium-voltage cable connection that takes one day instead of two.
Resilience
A Resilience Strategy and Implementation Agenda since 1 April 2026, diversified supply chains and analogue back-ups against cyber or physical threats.

Latest results

In H1 2026 investments rose to €710 million from €610 million, but only 107 MVA of capacity was added against an 858 MVA full-year target, as 460 MVA from two new substations and one expansion slipped to the second half. Operating income was €1,168 million (+€14 million), operating profit €239 million (H1 2025: €249 million) and profit after tax €148 million, with personnel costs up €50 million. Free cash flow was negative €325 million, FFO/Net Debt fell to 11.9% and solvency rose to 44.8%. A temporary connection freeze applies in part of Utrecht from 1 July 2026, and households may join a waiting list for the first time.

Investments and deals

Record grid investment
€1,294 million invested in 2025 (2024: €1,096 million), and over €2.4 billion planned in South Holland over the next three years.
Large supply contracts
A long-term contract with five suppliers for 293 power transformers in eight standard types, and a €3.5 billion tender awarded to 12 contractors for neighbourhood grids, with work started in April 2026.
Vianen distribution centre
A 34,000 m2 distribution centre in Vianen to support buying and delivering materials at scale.
Green financing
A €500 million green subordinated perpetual bond (4.25%) and a seventh €500 million green senior bond (3.625%) in 2026, an RCF raised to €1.5 billion and an EIB facility raised to €750 million.
Heat networks
NetVerder built almost eight kilometres of the Delft Heat Network and acquired an Eneco heating network in Delft; targets are 3,600 heat household equivalents for 2026 and 30,000-34,000 for 2030.

Challenges and risks

Worsening grid congestion
The demand-side waiting list grew by almost 800 applications in 2025; in Utrecht no new high-volume consumers can be connected except congestion relievers, and relief depends on TenneT expansions in 2033-2035.
Negative free cash flow and equity need
Free cash flow was negative €484 million in 2025 and is expected to stay negative; Stedin expects to need to strengthen its equity and is in discussions with its shareholders.
Technician shortage
The CEO said Stedin has only a third of the technicians needed for the planned grid expansion, and hires hundreds of people every month.
Delivery delays
Capacity additions lagged targets in 2025 (573 MVA versus 753 MVA) and H1 2026 because substation projects slipped; nitrogen regulation and land positions can cause further delays.
Cyber risk and affordability
Information security and cyber resilience risk was assessed higher in 2025, and rising grid tariffs put societal affordability of energy under pressure.

What leadership says

“We currently have only a third of the number of technicians needed to get the planned grid expansion on track.”

Trudy Onland, CEO · Management Scope interview, 24 June 2025

“Before investing tens of millions in network upgrades, we will first examine whether smart storage can be used to absorb peak loads. This would give us a few years of breathing space.”

Trudy Onland, CEO · Management Scope interview, 24 June 2025

“We are also increasing our productivity and capacity so that we can do more.”

Jaap Verhoeff, CFO · Stedin Group Annual Report 2025, 3 March 2026

“We also aim to scale innovations: first testing them on a small scale and then rolling out successful solutions more widely.”

Aline Arends, COO · Stedin Group Annual Report 2025, 3 March 2026

Where a supplier can help

Labour-saving tools and prefab
The technician shortage and the shift to modular, prefabricated construction favour suppliers of prefabricated substations, plug-in components and tools that cut field hours.
Flexibility and storage
The 600 MW flexible-capacity target for 2026 and the CEO's plan to test smart storage before upgrades open room for battery operators, Congestion Service Providers and energy-management software.
Grid digitalisation and AI
Digitally metering over 80% of MV substations and using AI for productivity call for sensors, data platforms and analytics partners.
Cybersecurity and resilience
The higher-rated cyber risk and the new Resilience Strategy point to security, supply-chain diversification and continuity services.
Recruitment and training
Hiring hundreds of people a month, training status holders and a new training centre in Rotterdam create demand for recruitment, onboarding and technical training providers.

Tamtam's reading of the priorities and challenges above, not the company's own words.

Selling to companies like Stedin?

Tamtam finds the companies that match your ideal customer, researches each account and tells you who to contact and when.

Find similar companies

Key documents

Read in full by Tamtam; each summary links to the document itself.

Questions about Stedin

What does Stedin do?

Stedin builds, operates and maintains electricity and gas distribution networks in most of South Holland, Utrecht and Zeeland, serving an area of approximately 5.6 million people. Through NetVerder it also develops heat and steam networks.

Who owns Stedin?

Stedin is owned by 61 Dutch municipalities, two provinces and the State of the Netherlands; the municipality of Rotterdam is the largest shareholder with approximately 27.9%.

What was Stedin's revenue in 2025?

Revenue was €2,300 million in 2025, with operating profit of €449 million and profit after tax of €278 million.

How many employees does Stedin have?

Stedin had 6,787 FTE at the end of 2025 and 7,109 FTE in H1 2026.

Who leads Stedin?

Trudy Onland has been CEO since 1 May 2025, with CFO Jaap Verhoeff, COO Aline Arends and CTO Timo Idema.

Written by Tamtam from the company's own published documents listed above, read in full. Figures are as those documents state them, for the periods they name. (2026-11-17)